Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
D07
114712
0058-058-049,B653
8/21/2020
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
exisiting precast interlocks
Type:
Plan
Question
Date:
7/23/2020 12:44:33 PM
Do we need to remove or reset existing precast interlocks unit? What is a specific for Scour countermeasure and its pay measurement?
Answer
Date:
7/30/2020 11:07:29 AM
Existing slope protection in the area of scour countermeasures will be removed as part of the excavation and subgrade preparation process.
Question
Date:
7/29/2020 2:15:41 PM
What Size precast concrete Armoring units are needed?
Answer
Date:
8/3/2020 3:51:46 PM
The special provision for Scour Countermeasures on pages 101-103 in the contract addresses the sizes in question.
Displaying questions 1 - 1 (of 1)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
3/28/2024 9:49:51 AM
2008