Advertisements   Division Home   Bid Results   Bid Tabs   Ad Report   VDOT Forms   ProjectWise
Project Info
Order Number UPC State Project Number Last Date to Post Questions
C87 101495 0671-087-667, C501, B666 8/21/2020
Search Questions
Search
Question Type  
    Export Q&A    
Question List
Subject: clarification needed on plan call out Type: Plan
Question Date: 7/14/2020 8:03:18 AM
on plan pages 4B, 5B, 7B, and 8B there is call out of "TSI" identified with a line similar to shoring. Can more information be provided on this item?  
Answer   Date: 7/14/2020 2:11:20 PM
TSI stands for Temporary Slope Interruptor. It is an erosion control measure used on tall and steep slopes. Please see the erosion control legend on sheet 2 and the VDOT Road & Bridge Standards as EC-15.  
 
Subject: Existing Plans Type: Plan
Question Date: 7/13/2020 8:11:44 AM
Please provide as-built plans for the existing bridges.  
Answer   Date: 7/14/2020 9:38:01 AM
No, the plans as provided are the only available plans.  
 
Subject: Permanent Sheet Piling Type: Permits
Question Date: 7/1/2020 4:32:22 PM
The contract documents contain the VDOT Contract Permits, Army Corps of Engineers Permits along with a set of 15 drawings. The permit verbiage states there will be Permanent Sheet Pile installations on B666 and B662. Where is the pay item for the Sheet Piling? Where is the Contract Drawing that shows the location of the Sheet Piling?  
Answer   Date: 7/10/2020 8:25:51 AM
Permanent Sheet Pile was removed from the contract. A revised environmental permit will be issued.  
 
Subject: Cofferdams Type: Plan
Question Date: 7/1/2020 4:27:10 PM
The contract documents contain the VDOT Contract Permits, Army Corps of Engineers Permits along with a set of 15 drawings. The permit drawings depict limits of Temporary Cofferdam Installations along with Rip Rap Limits as described in the permits. These drawing vary greatly from the Contract Drawings provided in the same solicitation. There are no cofferdams shown for the 662 bridge in the contract drawings, yet the entire area below this bridge is currently under water. Please confirm there are no cofferdams required for bridge 662.  
Answer   Date: 7/10/2020 8:25:22 AM
Temporary Cofferdam was removed from the overflow bridge and replaced with Temporary Silt Fence. A revised environmental permit will be issued.  
 
Subject: RipRap Type: Permits
Question Date: 7/1/2020 4:20:56 PM
The contract drawings depiction of Rip Rap and Stone Drainage Blanket installation differs from what is described in the Army Corps of Engineers Permit #19-400. Please confirm that riprap is only required at abutments as shown on contract drawings.  
Answer   Date: 7/10/2020 8:23:26 AM
Riprap is required at the abutments and as slope protection on the causeways. A revised environmental permit will be issued.  
 
Subject: project limits C-501 Type: Plan
Question Date: 6/29/2020 11:49:13 AM
C-501 Begin/End stations end and begin different from C-502. C-502 begins and ends at back of approach slabs. C-501 begins at the back of west approach slab but ends at eastern limit of proposed asphalt. IS the End station for C-501 correct??  
Answer   Date: 7/8/2020 10:21:49 AM
The Begin and End project stations for C-501 and C-502 are correct. These stations are defined by the limits of the full width typical section per the VDOT Roadway Design Manual.  
 

Displaying questions 1 - 6 (of 6)
Page: 1 First Previous Next Last