Order Number
UPC
State Project Number
Last Date to Post Questions
C96
116333
BR8C-968-526,N501
7/17/2020
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
Question Type must be selected.
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
Asphalt Milling
Type:
Bid Sheet
Question
Date:
7/17/2020 2:31:19 PM
Several of the project loctions have an asphalt overlay on top of the bridge structure, but there is no pay item for Asphalt Milling or Remove Asphalt Surface. Is this incidental to other pay items or should an item be added?
Answer
Date:
7/21/2020 2:26:01 PM
Type A Milling will be used to pay for asphalt milling on approaches and bridge decks
Subject:
3M Temporary Tape
Type:
Bid Sheet
Question
Date:
7/17/2020 9:14:07 AM
Regarding Bid items 54512, 54516, 54520.This temporary tape listed for these 3 lines shows Class II but I belive it should be Class III. I have attached the "Directive" from VDOT below. Please advise. Directive Effective immediately upon issuance of this directive, VDOT is migrating to solely using Type D-Class III tape for any projects in design phase and requiring the use of temporary tape markings as part of the MOT Plan. This is being done to improve work zone safety and help combat the troubling recent increase in work zone crashes. VDOT staff - Please share this directive with internal staff and consultant engineers responsible for the development of MOT plans for VDOT projects. This directive does not change the engineer’s decision-making process to decide whether to specify Type A, Type B, or Type D for the temporary pavement markings. However, if the decision is made to use Type D temporary tape, then D-III tape shall be specified. CO-TED is working to develop improved policies/best practices for determination of appropriate temporary marking type.
Answer
Date:
7/17/2020 12:59:01 PM
We will review this subject and address the Class II vs Class III discrepancy during the pre-construction meeting.
Subject:
Definition of Contract Term
Type:
Proposal
Question
Date:
7/16/2020 3:42:47 PM
On page 109 of the Proposal, section 104.01 states that "during the term of the Contract, the Department will issue Task Orders to the Contractor with a cumulative value will equal or exceed 70 percent of the original value of the Contract." For the purpose of this section, does the phrase "term of the contract" refer to the original term (NTP to 11/30/21) or a term that may include up to 3 renewable years (NTP to 11/30/23)?
Answer
Date:
7/21/2020 1:08:21 PM
Term refers to the initial term, any subsequent term/renewal would be considered separate, in addition to the original term.
Subject:
Warren 1013 - NS Railroad
Type:
Proposal
Question
Date:
7/14/2020 2:42:57 PM
Will any work on the structure 1013 location in Warren Va occur outside the limits of the parapet such that Railroad insurance will be required.
Answer
Date:
7/16/2020 2:11:32 PM
Work identified for this structure is on the deck surface and between rails. No work is currently planned that will require RR Insurance at this location.
Subject:
MODIFY STEEL BEAM END
Type:
Proposal
Question
Date:
7/14/2020 2:40:25 PM
Can you provide details or a description of what will be required for the Modify Steel Beam End Bid Item
Answer
Date:
7/16/2020 2:11:07 PM
The Modify Steel Beam End pay item will be used to trim jammed beam ends where directed by the Engineer, per Section 426.
Subject:
MOT
Type:
Proposal
Question
Date:
7/14/2020 2:37:35 PM
For the projects with Type A milling, will traffic be allowed to run on milled surface prior to the overlay? Similarly, for projects with Hydro-demolition, will traffic be allowed to run on the demo'd surface prior to the overlay?
Answer
Date:
7/16/2020 2:10:42 PM
raffic will be allowed to run on surfaces receiving Type A Milling (Mechanical). Transition areas and rideability per the Specifications will be required and evaluated by the Engineer. Traffic will NOT be allowed to run on surfaces receiving Type A Hydro-Demolition.
Subject:
For the REPLACE HIGH STRENGTH GROUT Bid ITem, what are the removal limits for the existing grout?
Type:
Proposal
Question
Date:
7/14/2020 2:31:18 PM
Answer
Date:
7/21/2020 2:25:34 PM
Replace High Strength Grout shall be accomplished in accordance with Section 412 of the specifications. The limits of grout removal typically involves removing grout from existing longitudinal shear keys between prestressed members.
Subject:
As Built Plans
Type:
Plan
Question
Date:
7/7/2020 5:33:22 PM
Can as built plans be made available on ProjectWise?
Answer
Date:
7/21/2020 2:25:19 PM
No - plans will not be made available on ProjectWise
Displaying questions 1 - 8 (of 8)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
4/25/2024 5:41:18 AM
2008