Question
|
|
Date:
|
6/12/2020 12:20:20 PM
|
The plans (lighting & traffic signal) show a total of 1,775 lf and the bid sheet shows 1,550 lf. Can you verify the correct quantity?
|
Answer
|
Date:
|
6/12/2020 3:39:09 PM
|
The total amount required for Trench Excavation (lighting and signal) is 1775 LF as shown on plan summaries 10(2) and 11(2) in the addendum
|
|
|
Question
|
|
Date:
|
6/15/2020 10:50:56 AM
|
Will the bid sheet be corrected?
|
Answer
|
Date:
|
6/15/2020 3:45:43 PM
|
No, the bid sheet will not be revised as this is a unit price contract that would allow for potential overruns/underruns.
|
|
|
Question
|
|
Date:
|
6/12/2020 12:18:13 PM
|
Can you verify the "Lighting-Lighting LED Luminaire, Pole Mounted Ty A" for a quantity of 2 on sheet(2) is supposed to be listed under the traffic signal? This item suddenly appeared between the original and this addendum. It specifically states on 10(3) that these are included in the lighting plan.
|
Answer
|
Date:
|
6/12/2020 2:56:39 PM
|
The quantity of 2 Lighting Luminaires,Pole Mounted TY A are correctly summarized
on sheet 11(2) for lighting the entrance on plan 11(5) and are not for the traffic signal on plan 10(3). This item was in the original bid plans.
|
|
|
Question
|
|
Date:
|
6/15/2020 10:50:34 AM
|
Will this be deleted from the plans?
|
Answer
|
Date:
|
6/16/2020 1:20:46 PM
|
Two mast arm pole mounted luminaires summarized, along with the 2 LP-2 light pole mounted luminaires, on the lighting item summary sheet 11(2) were inadvertently added to the signal plans summary sheet, 10(2). The luminaires inadvertently added to Sheet 10(2) will not be deleted before bids are due to be submitted.
|
|
|
Question
|
|
Date:
|
6/12/2020 11:20:18 AM
|
Proposal Line #0720 -Is the ATC cabinet a 16 channel or 32 channel?
|
Answer
|
Date:
|
6/12/2020 2:42:43 PM
|
The ATC cabinet should have 16 channels.
|
|
|
Question
|
|
Date:
|
6/4/2020 11:04:45 AM
|
The legend and bid item (#0560) list this pole as a Type E2 w/75' mast arm. The mast arm in the bid items (#0590) is listed as Case 1 loading. Shouldn't this arm be listed as Case 2 loading to match the E2 upright?
|
Answer
|
Date:
|
6/8/2020 8:02:21 AM
|
No, the 75' mast arms shall be Case 1 loading. This loading will be noted on plan sheet 10(3) and included in the addendum.
|
|
|
Question
|
|
Date:
|
6/3/2020 9:58:01 AM
|
On Sheet 10(4), please confirm whether poles are existing.
|
Answer
|
Date:
|
6/4/2020 9:06:07 AM
|
On sheet 10(4),yes, the poles shown are existing. The legend on the plan will be revised to reflect that and the plan will be included in the project addendum.
|
|
|
Question
|
|
Date:
|
6/1/2020 4:25:53 PM
|
Quantity summaries for the lighting and traffic signal show electrical service SE-8 ty B. Plan sheet 11(3) states electrical service SE-8 to be shared with Signal Plan. Signal plan sheet 10(3) conduit run T states grounding for SE-3 and the inset for the Northeast Quadrant specify an SE-3 as well. Can you clarify how many and which electrical service is required?
|
Answer
|
Date:
|
6/4/2020 9:07:35 AM
|
The quantity summary is correct that electrical service will be Type SE-8. On plan 10(3), the notations on conduit run T and the inset for the NE Quadrant will be revised accordingly and included in the
upcoming addendum.
|
|
|
Question
|
|
Date:
|
5/19/2020 11:11:33 AM
|
Will batteries be added to this project?
|
Answer
|
Date:
|
5/20/2020 10:30:35 AM
|
Yes, an uninterruptible power supply battery pack is needed for the traffic signal. This item will be added to plan sheet 10(2) and included by addendum.
|
|
|
Question
|
|
Date:
|
5/6/2020 3:16:11 PM
|
Please clarify the quantity of the S2 boxes. The bid sheet has 7 and the traffic signal quantity summary has 4.
|
Answer
|
Date:
|
5/7/2020 11:36:55 AM
|
An addendum to address quantity issues will be issued the second week in
June.
|
|
|
Question
|
|
Date:
|
6/11/2020 2:04:21 PM
|
Are you still planning on posting the addendum this week? Suppliers will need time to respond.
|
Answer
|
Date:
|
6/11/2020 7:16:25 PM
|
Yes, the revision will be posted first thing tomorrow morning.
|
|
|
Question
|
|
Date:
|
5/6/2020 3:15:14 PM
|
Please clarify the quantity of the S1 boxes. The bid sheet has 15, TS has 17, and Lighting has 2. Should there be 15 or 19?
|
Answer
1 previous answer(s)
|
Date:
|
5/13/2020 10:45:42 AM
|
We have verified the quantity on the Traffic and; Lighting Summaries are incorrect. The summaries will be revised to reflect a total of 18 S1 boxes. Plan 10(3) has 14, Plan 10(4) has 1 and plan 11(6) has 3. An addendum to address quantity items will be issued the second week in June
|
|
|
Question
|
|
Date:
|
5/6/2020 3:13:32 PM
|
|
Answer
|
Date:
|
|
|
|
|