Advertisements
Division Home
Bid Results
Bid Tabs
Ad Report
VDOT Forms
Login Or Create Account
Project Info
Order Number
UPC
State Project Number
Last Date to Post Questions
C49
107020
0037-034-876, N501
4/17/2020
Search Questions
Search
Question Type
All
Plan
Proposal
Bid Sheet
Permits
Specifications
Other
The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered.
Export Q&A
Question List
Subject:
SM-9.5A
Type:
Specifications
Question
Date:
4/8/2020 8:00:26 AM
Can SM-9.5AL be used on the shoulders?
Answer
Date:
4/9/2020 6:22:31 PM
SM-9.5AL can not be used on the shoulders.
Subject:
Aggregate Base Material Type I, No. 21-B
Type:
Proposal
Question
Date:
4/7/2020 8:32:47 AM
The 21-B quantity on the guardrail summary sheets doesn't add up to the bid item quantity amount. Does the department plan on placing the material in other locations?
Answer
Date:
4/7/2020 9:49:12 AM
The 21-B quantities are also to be used for the Guardrail Terminal Site Preparation as well as shoulder stone.
Question
Date:
4/7/2020 1:26:24 PM
How wide will the stone shoulders be? Will the stone shoulders be placed at the same locations as the widening?
Answer
Date:
4/9/2020 8:01:26 PM
The stone shoulder will be placed as needed along the pavement widening to match existing shoulders (to fill in low spots) and will be paid for by the ton.
Subject:
Traffic Control
Type:
Proposal
Question
Date:
4/6/2020 3:49:11 PM
The proposal does not have an arrow board bid item. How will the arrow board be paid or does it need to be incidental to another item?
Answer
Date:
4/13/2020 1:09:14 PM
Revision has added electronic arrow board pay item.
Subject:
Erosion Control Plan
Type:
Proposal
Question
Date:
4/3/2020 9:17:40 AM
On page 160 line number 3 it states that suitable excavated material is to be re-used as shoulder buildup material and be placed and compacted along the edge of the newly widened road as needed. How will this be paid?
Answer
Date:
4/13/2020 1:06:01 PM
Revision has added Machining Shoulders to pay for suitable excavated material that is to be re-used as shoulder buildup material.
Subject:
Plans/Proposal
Type:
Proposal
Question
Date:
3/30/2020 9:00:21 AM
When will the plans/proposal be uploaded to ProjectWise?
Answer
Date:
3/30/2020 9:22:41 AM
The project folder permissions have been corrected.
Displaying questions 1 - 5 (of 5)
Page:
1
First
Previous
Next
Last
Construction Advertisement Bulletin Board (CABB)
Update Profile
CABB v2.0
© 2008 Virginia Department of Transportation
3/28/2024 2:18:53 PM
2008