    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: Bid items April 10th revision dont match ASSHTO bid format Type: Bid Sheet
Question Date: 4/20/2020 12:57:34 PM
The AASHTOWare Project Bid sheets, quantities and bid items do not match the bid items shown in the April 10th revision sheets. Will we still bid the AASHTOWare quantities?  
Answer   Date: 4/21/2020 8:22:25 AM
The AASHTOWare Project Bid sheets and BIDX, quantities and bid items have been updated to reflect the April 10th revision sheets. Please download a new bid file to prepare your bids for submittal tomorrow.  
 
Subject: ADDITIONAL PLAN SHEETS Type: Plan
Question Date: 4/13/2020 8:39:28 AM
I am trying to upload the new plan sheets per the April 10 revision. I do not see plan sheet 0013-001-693-C501-00 on Projectwise.  
Answer   Date:
 
 
Subject: 20' Lum Arms - Item# 1450 Type: Plan
Question Date: 3/17/2020 10:04:21 AM
Sheet 4(3) of UPC 111709 Plans shows 20' lum arms on LP-2 poles which are for tenon mount. It looks like these lum arms are intended for the Type F signal poles shown on Sheet 6(3) of the plans for UPC 111707 which list no lum arms but they are drawn on the poles. Please confirm.  
Answer   Date: 3/18/2020 12:25:05 PM
The poles on sheet 4(3) for UPC 111709 denotes LP-1 poles and they can be found on summary sheet 4(1A) as well as the 20’ Luminaire arms. See detail on sheet 4(2). UPC 111707 sheet 6(3) refers you to sheet 6(2) for Luminaire details. Sheet 6(1B) shows 2 ea 20’ Luminaire arms.  
 
Question Date: 3/18/2020 1:50:04 PM
Sheet 4(3) shows LP-2 poles with 20' luminaire arm and cobra heads. Sheet 4(1A) only shows the light pole and the 210 watt luminaire pole mount. Where is the pay item on the quantity summary for the 20' luminaire arm? Also, the drawing on sheet 4(2) is a light pole with a cobra head no luminaire arm. None of the sheets match for the lighting in this section.  
Answer   Date:
 
 
Subject: UPS Items Type: Plan
Question Date: 3/17/2020 9:58:53 AM
After the 3/13 revision both signal plans show a UPS Unit and Battery Pack, the line items only show a quantity of 1 each. Should this be 2?  
Answer   Date: 3/18/2020 1:22:04 PM
Yes, this quantity should be 2.  
 
Question Date: 3/18/2020 1:59:57 PM
Will additional quantity be added by addendum?  
Answer   1 previous answer(s) Date: 3/18/2020 2:03:26 PM
No, any quantity overruns will be handled in accordance with Specification 104.02(a).  
 
Subject: Line Item Issues after 3/13/20 Revision Type: Other
Question Date: 3/17/2020 9:47:32 AM
Item 0960 Conc Sign Found STP-1 Ty A drawings show 20 line item shows 19 Item 1210 Rem Exist Sign Str Ty WP-1 & Salv drawings show 1 line item shows 4 Item 1250 Rem Exist Sign Panel & Salv drawings show 2 line item shows 1 Item 1610 Trench Excavation ECI-1 drawings show 1400 line item shows 2550 Please advise.  
Answer   Date: 3/18/2020 1:23:51 PM
The pay item for 0960/50485 CONCRETE SIGN FOUNDATION STP-1, TYPE A, UPC 111710 has 8 and UPC 111707 has 12 for a total of 20 Item #1210/51963 REMOVE EXISTING SIGN STRUCTURE TY WP-1 AND SALVAGE has a quantity of 4 EA Item #1250/51963 REMOVE EXISTING SIGN PANEL AND SALVAGE has a quantity of 1 EA (this combines with 1210/51963 above) Item 1610/56200 TRENCB EXCAVATION ECI-1 the bid item is correct with 2,550.00  
 
Question Date: 3/18/2020 2:10:43 PM
Line item 1210 and 1250 are completely different and can not be priced the same. Even combined the line items and the drawings do not match. Will the 0960 line item be adjusted via addendum? Where is the extra 1,150 of trench on the drawings? It is very important for the line items and drawings to match for bidding and pricing material.  
Answer   Date:
 
 
Subject: Item # 1570 Type: Proposal
Question Date: 3/10/2020 4:42:56 PM
Bid item 1570 calls out 1,355 LF of bored 3”. Sheet 6 (1B) calls out 780 LF. Which is correct.  
Answer   Date: 3/18/2020 12:25:42 PM
The bid sheet is correct. The bid sheet consists of 3 projects. Additional quantity can be found on sheet 7(2) for project 0013-0001-693, C501 UPC 111710.  
 
Subject: Item 1560 Type: Proposal
Question Date: 3/10/2020 4:42:17 PM
Bid item 1560 calls out 370 LF of bored 2”. Sheet 6 (1B) calls out 255 LF. Which is correct.  
Answer   Date: 3/18/2020 12:25:57 PM
The bid sheet is correct. The bid sheet consists of 3 projects. Additional quantities can be found on sheet 4(1A) for project 0013-0001-694, C501 UPC 111709.  
 
Subject: Item 1500 Type: Proposal
Question Date: 3/10/2020 4:41:37 PM
Bid item 1500 calls out 17 JB-S2. Sheet 6 (1B) calls out 10 JB-S2. Which is correct?  
Answer   Date: 3/18/2020 12:26:22 PM
The correct quantity for this bid item is 11. Summary on sheet 6(1B) calls out for 10 for project 0013-001-695,C501 UPC 111707 and summary on sheet 4(1a) has 1 for project 0013-001-694,C501 UPC 111709.  
 
Subject: Item 1490 Type: Proposal
Question Date: 3/10/2020 4:40:58 PM
Bid item 1490 calls out 7 JB-S1. Sheet 6 (1B) calls out 1 JB-S1. Which is correct?  
Answer   Date: 3/18/2020 12:26:47 PM
The bid sheet is correct. The additional quantity can be found on sheet 7(2) for project 0013-0001-693, C501 UPC 111710.  
 
Subject: Item 1420 Type: Proposal
Question Date: 3/10/2020 4:38:46 PM
Bid item 1420 calls out 3,495 LF of 8 conductor cable. Sheet 6 (1B) calls out 765 LF. Which is correct?  
Answer   Date: 3/18/2020 12:27:04 PM
Additional quantity can be found on sheets 4(1A) for 0013-001-694, C501 UPC 111709 and sheet 7(2) for project 0013-0001- 693, C501 UPC 111710.  
 

Displaying questions 1 - 10 (of 31)