Project Info
Order Number UPC State Project Number Last Date to Post Questions
C31 107061 0419-080-876, C501 4/17/2020
Search Questions
Search
Question Type  
    The last date to post questions has passed. Any questions posed 72 hours before the letting date may not be answered. Export Q&A    
Question List
Subject: 8" Sanitary Sewer and MH "A" Type: Plan
Question Date: 3/20/2020 9:12:16 AM
RE: Plan Sheet 8(4) and Plan Sheet 8(10) The plan location for San MH "A" is in the outside eastbound travel lane of Rte. 419. This structure has a depth of 12 feet. This structure is also a drop manhole will flow across all lanes of Rte. 419. Plans also show a 10' connection pipe at a depth of 12 feet which extends into the inside travel lane of eastbound Rte. 419. In order to accomplish this work as designed, we will not be able to maintain one lane of traffic on eastbound Rte. 419. The MOT plans do not address the detour that will be required in order to complete this work. The Utility plans do not address the pump around that will be required for the work or provide the flow rate of the exiting pipe. Please address the MOT for this portion of the work. Please also address permissible means of pumping the existing sewer across all lanes of Rte. 419 during installation of MH "A" and the 8" DI connection pipe. Please advise how this work is to be accomplished  
Answer   Date: 3/24/2020 4:48:49 PM
We will be addressing this question with an upcoming addendum/revision.  
 
Subject: Temporary Signal for Intersection 1, 2, & 3 Type: Other
Question Date: 3/16/2020 9:32:48 AM
Has the department established that there is enough right-of-way to install down guys for the wood poles? Most of the locations seem to show that there is not enough room. If not, will the department provide an alternate plan for the temporary and absorb the cost?  
Answer   Date: 3/17/2020 10:59:09 AM
At the intersection of Route 419 and S Peak Blvd, more than 8' of construction easement is provided behind the temporary wood pole F. For all other locations, more than 10' of construction easement is provided behind the temporary poles. The Contractor should design the direction, number and type as necessary for guys. In locations where easement is limited, the vertical type of guy can be considered as shown in standard WD-2.  
 
Subject: Video Detection for Temporary Signal Type: Other
Question Date: 3/16/2020 9:28:34 AM
Will the department require NSync cameras for the temporary signal at all 3 locations?  
Answer   Date: 3/17/2020 10:58:36 AM
The temporary signals should use the existing controllers and the existing signal coordination / synchronization should be maintained. The Contractor should choose the correct type of cameras accordingly.  
 
Subject: S. Peak & Electric Rd. Type: Plan
Question Date: 3/16/2020 9:19:18 AM
This intersection shows a Type F pole which according to the spec has the loading for a luminaire . Should this be a Type C pole as there is no luminaire on the drawings. Please clarify.  
Answer   1 previous answer(s) Date: 3/17/2020 11:39:57 AM
A Type C pole will be added to the Contract by work order for this location.  
 
Subject: Temp Shoring Type: Proposal
Question Date: 2/26/2020 10:05:24 AM
In regards to the temporary shoring, per the proposal existing plans can be provided upon request of the existing sign structure. Please provide existing plans of the sign structure to assist in design of shoring.  
Answer   Date: 3/5/2020 8:11:17 AM
Documents have been uploaded to ProjectWise.  
 

Displaying questions 1 - 5 (of 5)