Will the road (Old Buckingham) be fully closed for the duration of the Project?
Answer History
Previous Answers PostDate
Route 13, Old Buckingham Road shall only be closed and the detour implemented after the Contractual NTP of June 15, 2020. The detour must be removed on or before the final completion date of August 31, 2020. 10/22/2019
Route 13, Old Buckingham Road shall only be closed and the detour implemented after the Contractual NTP of June 15, 2020. The detour may remain in place until Final Acceptance. 10/16/2019