The As-Builts provided show the existing structure on spread footing foundations without any piles. Please confirm there are no piles in the existing bridge foundations ? Does VDOT have any record of temporary piles or cofferdams left in place from construction of the existing bridge that could present conflicts/obstructions for the new piles and/or cofferdams ? How are Obstructions to be handled if they are encountered ?
Answer History
Previous Answers PostDate
Existing SBL bridge substructure units have spread footings according to as-built drawings. Pier footings should be absent of any piles. Any subsurface obstructions not shown on the plans or geotechnical borings would be considered a changed condition and handled as a change order. 9/20/2019
Any subsurface obstructions not shown on the plans or geotechnical borings would be considered a changed condition and handled as a change order. 9/20/2019