Question Date: 3/15/2019
The quantity stated on Sheet 26(6) for Wall F2 appears to be four times the actual quantity. Please confirm. The same would apply to the question related to Structure Excavation.
Answer History
Previous Answers PostDate
The quantity for the A4 concrete and the structural excavation should be 405 CY instead of 1,510 CY. 3/18/2019
The bridge over Linkhorn Bay was inspected in 2013; no asbestos was discovered. However, the inspector cannot say with 100% certainty that there is no asbestos, as it is possible that some materials are hidden. For that reason, the specification for removal of asbestos is included for this scenario. 3/18/2019