Yes, the contractor can work in one lane (same lane) on both the South Island and North Island at the same time contingent on scheduling approval in LCAMS. Yes the contractor can work on both Northbound and Southbound lanes at the same time contingent on scheduling approval in LCAMS. It should be noted that the work at MMMBT competes with HRBT and JRB (Same Direction). It would be expected that the contractor work with Tunnel Maintenance personnel and other contractors attempting to get work done at the three facilities and be prepared to work in a different direction in some cases to allow everyone to work together.
|
10/17/2018
|