Question
Question
Date:
2/20/2018
Since the Salem District Plant Mix Proposals include a larger quantity of SMA this season than normal, would the Department consider extending the SMA work date until November 1, 2018 for this project?
Answer History
Previous Answers
PostDate
No, this work needs to be completed as specified.
2/26/2018
No, this work needs to be completed this calendar year and not go through another winter.
2/26/2018