Project Info
Order Number State Project Number Last Date to Post Questions
M32 (NFO)9999-966-S45,N501 9/22/2017
Question
Question Date: 9/8/2017
There is a bid item for Flagger Service(300 hours). On Page 78 of the contract, in the "Flagger Service" paragraph, it states that any hours required beyond the contract numbers will be paid at only $15 per hour(regardless of the bid rate). Is this correct? Note that the Davis Bacon rate for a flagger in some locations for this project is $13.64 per hour.
Answer History
Previous Answers PostDate
The bid item for Flagger Service is being removed by addendum. Flagger Service will not be a separate bid item and the price will need to be included in the Lump Sum Maintenance of Traffic bid item. The language in the Special Provision for Section 512- Maintaining Traffic – Non-Schedules (Lump Sum) is correct and will apply to this contract. 9/14/2017
Please see an addendum to be issued this week. 9/11/2017