Last Date to Post Questions
263
(NFO)PM2B-009-F17,P401
5/19/2017
Question
Question
Date:
5/3/2017
Since this project involves night work and mix types that have a 50 degree spec, would the department consider extending the completion date until 6/29/2018?
Answer History
Previous Answers
PostDate
The Department has reconsidered and will revise the completion date to June 30, 2018.
5/10/2017
No, the completion date is June 1, 2018.
5/3/2017