Ref Sheet 2E
1) The borrow quantity does not match the calculation given. The borrow quantity given seems to be for Traffic Control Phase 1 only, but the diagram/summary does not reflect this.
2) The job appears to be a surplus haul off, but no surplus is indicated on the grading diagram.
3) Do the cut quantities for the detours include the removal of the temporary crossovers during Stage 4? It does not appear so.
|