Question
Question
Date:
11/13/2020
The SPCN on Sheet 7 of the proposal for Rock Excavation states that "work shall consist of excavation of solid rock for trenches..". Does this include all of the utility, storm sewer, culvert, and conduit installations?
Answer History
Previous Answers
PostDate
Section 302 and Section 520 of the 2020 VDOT Road and Bridge Specifications state that the price of the excavation associated with pipe, water and sewer items, and encasement pipes are included in the cost of the pipe or water and/or sewer items or encasement pipes. Section 302 and Section 520 do not differentiate whether the trench excavation is rock excavation or not. Rock Excavation measurement and payment of trench excavation is limited to signal and lighting conduits and signal and light pole foundations
11/17/2020
Section 302 and Section 520 of the 2020 VDOT Road and Bridge Specifications state that the price of the excavation associated with pipe, water and sewer items, and encasement pipes are included in the cost of the pipe or water and/or sewer items or encasement pipes. Section 302 and Section 520 do not differentiate whether the trench excavation is rock excavation or not.
11/16/2020