Addendum 1 stated to replace (bridge) plan sheets 2, 9,16,20A, and 21. There was no previous sheet 20A (Bridge Conduit System), only sheet 20 (CPSR Rail). The updated plan sheets on projectwise no longer contain the original plan sheet 20. Was this sheet supposed to be removed? If not can it be added back to the plans?
|